Independent University Bangladesh Campus, 10-storied building with 2 basements, auditorium and other facilities.

Radisson Water Garden Hotel, 9-storied building with basement 30,500m 2 floor area with other facilities

Dhaka Sheraton Hotel- Office Block & Health Complex, 7-storied Shopping cum offfice building having basement of 16,500 sft. & 5-storied health club including air conditioning, electrification, plumbing and sanitary works.

 DARBAR HALL Bangabhaban, investigation & assessment of damages and repair and renovation of DARBAR HALL.

 US Chencery Builing at Dhaka. Concreting, Rebar & Formwork of the Chancery Builing.

Third Buriganga Bridge, Basila, Mohammadpur, Dhaka.

Construction of 500 Bed General Hospital at Khilgaon, Mugdapara, Dhaka Construction of 500 Bed General Hospital at Khilgaon, Mugda, Dhaka.

NLI Tower, 12-storied builing with three basement and associated works.

SRNDP-3 Bhanga-Bhatiapara Road.

Construction of Flyover at Mirpur Airport Road  & Overpass at Bannani Rail Crossing.

Civil & Building Works of 100 MW Power Plant Haridaspur, Gopalgonj.

COMPLETED PROJECTS


Project Name Employer Discription Completion/Expected Completion Date
ROADS, HIGHWAYS, BRIDGES AND FLYOVERS

20-storied Police Qtr., Nilkhet, Dhaka on turn-key basis in association with Shaheedullah and Associates Ltd.

Public Works Department (PWD)

Design & construction of residential tower having 10 units of 800 Sft. each per floor along with associated works.

2012
FUNCTIONAL BUILDINGS
Superstructure & basements of Independent University, Bangladesh Campus at Bashundhara, Dhaka.Independent Universtiy Bangladesh.2 basements and 500,000 sft floor area in10-storied academic block, 6-storied lab. blocks incl. double height Gymnasium, 6-storied library block, 4-storied registration block, 4-storied administrative block and one auditorium having seating capacity for 700 persons.2010
20-storied NLI-Tower (1st Phase: up to 12 floors including 3 basement floors) at 54, Kawran Bazar, Dhaka.National Life Insurance Co. Ltd.Upto 12 floors plus 2 basemnt floor with civil, sanitary, plumbing and internal and external electrification works and fire fighting works.2009
Upgradation of KushtiaSadar Hospital from 100 to 250 bed under HPPP, IDA Credit No. 3101- BD, C/Package # W(PWD)/HK-3Public Works Department (PWD)Renovation and Upgradation of Hospital from 100 to 250 bed including civil, sanitary & plumbing and electrical works.2006
Supply, fabrication, Installation & testing of Aluminium glazing works & glazed roofing works at Water Garden Hotel at Dhaka CantonmentSena Hotel Devel-opments Limited.Aluminium Glazing, doors & window works of 5-star hotel building with imported Aluminium& Glass. Dome with fibre glass sheet at Canopy.2005
Auditorium at BMA Bhatiary (Job No. 182 of 93-94), ChittagongMilitary Engineering Services (MES)1,230 seated Auditorium inculding internal services, site development & associated works.2004
9-storied superstructure work incl. construction of foundation and basement floor of Water Garden Hotel at Dhaka Cantonment.Sena Hotel Develo-pments Ltd.9-storied superstructure work including construction of Foundation and single level basement floor.2004
HRC Bhaban at 46 Kawran Bazar, DhakaHamid Properties Ltd.12-storied building with 2-basements, sanitary, electrical, finishing works.2004
Hotel Building and supply and installation of Furniture, Furnishing and Equipment (FF&E) works for the new block of Five Star Dhaka Sheraton Hotel (presently Ruposhi Bangla).Bangladesh Services Ltd.10-storied building with two basement floors, one mezzanine floor plus seven floors of Hotel facilities having a total built-up area of 13,502 Sqm incl. supply & inst. of furniture, furnishing & equipment.2003
5-storey of 10 storied City Bhaban Complex of Rajshahi City Corporation at Greater Road, RajshahiRajshahi City Corporation5-storey City Bhaban with 10 storied foundation with piling & associated works.2002
Construction of National Art Gallery including supply & installation of E-M Services at Segunbagicha, Dhaka.Bangladesh Shilpakala Academy.2-storey of National Art Gallery with 8-storied foundation incl. supply & installation of Electro-Mechanical Services.2002
Multistoried office cum Residential building of JMBA at Banani, Dhaka.Jamuna Multipurpose Bridge Authority (presently BBA)4 floors including associated works of a 14-storied office-cum-residential building with 2 basements2001
New Elementary School/Library and physical facilities building of American International School at Baridhara, DhakaAmerican International School3-storied school building (30,000 Sft.) after demolishing existing structure, E-M works with 750 KVA sub-station, 500 kwt generator, hydraulic lift, both split & package types of air-conditioner, fire fighting& fire detection works. Physical education facilities building over existing swimming pool, steel superstructure of 50'-0" height with facilities of Basket & Volley ball courts.2000
18-storied Head Office building of Islami Bank Bangladesh Limited at 40, Dilkusha C/A, DhakaIslami Bank Bangladesh Ltd.18-storied plus basement, office building incl. Sanitary, Plumbing, Water Supply, Internal Electrification and Fire Protection works, supply & installation of one car lift.2000
Toll Plaza, Security Building & Security tunnel at East Approach of JMBP (presently BBA), Contract #3, Tangail on sub-contract basis.Samwhan Corporation2-storied Security Building, Security tunnel & Toll Plaza including Sanitary, Plumbing & internal electrification works.1997
7-storied Shopping Complex cum Office building & 5-storied Health Club of Dhaka Sheraton Hotel, DhakaBangladesh Services Ltd.7-storied Shopping cum Office building having basement of 16,500 sft. and @12,000 sft. each floor & 5-storied health club @5,500 sft. each floor. Also includes air conditioning, electrification, plumbing and sanitary works.1996
Rural Employment Sector Program (RESP) HQ Building at Badarpur, FaridpurLocal Govt. Engg. Bureau.4-storied Office building & 1-storied Conference block incl. sanitary & plumbing works along with 2m high b/walls.1990
British High Commission Amenities Centre & British High Commissioner's new residence at Baridhara, DhakaBritish High Comm-ission, Dhaka.2 buildings on pile foundation and 2-storied British High Commissioner's Residence incl. servants block, 2 nos. of Swimming Pools, Tennis Court and boundary wall. Also incl. electrial and mechanical works, sewage treatment plant & sound proofing arrangement in the Hall room.1989
Administrative building of River Research Institute at FaridpurBangladesh Water Development BoardBoard Administrative building having floor area of1 9,368 sft. built on 217 nos. cast-in-situ piles incl. Civil,Sanitary, Plumbing & Electrical works.1989
Concreting, rebar & form work of US Embassy Chancery Building at Baridhara, DhakaM/S. Daelim Industrial Co. Ltd.Concreting-11,000 cum, Rebar work-1,200 tons and formwork-33,000 sqm.1987
FACTORY COMPLEX
7-storied Factory Building of Fashion Fourm Ltd. at Zamgara, Savar, DhakaFashion Forum Ltd.5 storied out of 7 storied having total floor area of 15,600m2 is built combinedly on 35 nos. of well foundation having diameter of 8 feet & 5 feet and length of 36 feet and 30 nos. cast in situ piles with post tensioned pre-stressed concrete slab.2007
Factory Complex of Mir Ceramic Ltd. at North Mawna, Sreepur, GazipurMir Ceramic Ltd.Factory building incl. Civil, E & M works. Also includes supply, inst. and comm. of 2 nos. Generators of 1430 KVA and 175 KVA, 2 nos. indoor type electrical substation of 800 KVA and 500 KVA incl. HT & LT Switch Gears and Transformer.2003
Factory Complex of Mir Cement Ltd. at GanganagarMurapara, Rupganj, NarayanganjMir Cement Ltd.Factory building incl. Civil, E & M works, supply, installaiton& commissioning of 175 KVA Generator set, 2 nos. of indoor type sub-station & Jetty2002
Pharmaceutical building works RPR &Fisons at Tongi, Gazipur in J/Venture with PSG.Rhone Poulenc Rorer Bangladesh Ltd.Building works incl. mechanical & electrical services for microlides, solids, creams and liquid facilities of T-4 building Refurbishment and CPR Building and Bottle Warehouse.2000
Civil & Building works of KAFCO, fertilizer factory on sub-contract basisMitsui & Co. Ltd.Equipment foundations & const. of different civil structures like cooling tower, clarifier, mobile equipment shop, chlorine storage, chemical storage, substation bldg., u/g water reservoirs, pre-cast manhole pits, boundary fencing and slope protection work.1994
Design & Construction of the factory building of Tootal Thread Bangladesh Ltd. at Chittagong.Tootal Thread Bangladesh Ltd.Factory building, 17,800 Sft., 10' to 40' ht., steel trusses. Also includes Deep tube well, pump house, different tanks & sumps, internal roads, culvert & drains.1990
Factory building of Setabganj Sugar Mills Ltd., Dinajpur.Bangladesh Sugar and Food Industries Corporation.Factory building having a floor area of 88,000 Sft. and ht. of 68' built partly on 282 nos.of 18 m long 300 mm square pre-cast RCC driven piles and partly on RCC spread footing & 750 M tons of structural steel work.1982
HOSPITAL COMPLEX
IBN SINA Hospital at Plot #66, road #15/A, Dhanmondi, DhakaMr. S. Alam& IBN Sina Trust6-storied Hospital Building with ancillary works.2007
Thana Health Complex at Haimchar, ChandpurMinistry of Health & Family WelfareHospital Building & Staff Quarter including site development, overhead water tank, boundary wall & internal road.1997
Out Patient Building & Toilet Blocks at Chittagong Medical College Hospital, ChittagongMinistry of Health & Family Welfare4-storied Building along with 4 nos. of 5-storied Toilet blocks incl. civil, E-M, Sanitary & Plumbing works.1996
Establishment of Thana Health Complex at Modhukhali, FaridpurMinistry of Health & Family Welfare6 flats, 3-storied each, 8 flats, 4-storied each, 4 flats, 2-storied each along with 1-storied Doctor's &Nurses Dormitoryincl site development work.1996
Thana Health Complex at Harirampur, ManikgonjMinistry of Health & Family WelfareHospital Building & Staff Quarter including site development work.1992
CYCLONE SHELTERS AND VILLAGE TRANSFORMATION
Village Transformation at SIDR affected Majher Char, PirojpurBritish Business Group (BBG)66 Houses, Water Harvesting System, Rehab. of earthen road & pipe Culverts2009
Multi-Purpose Cyclone Shelters under Japanese Grant on Sub-Contract basis at Mirsarai, Chittagong.Shimizu Corporation3 nos. 2-storied School cum Cyclone Shelters built on pile foundation, as cast fair face concreting and associated works.1997
Multi-purpose Cyclone Shelter used for School, Mosque & Cyclone Shelter at Bandar and KotwaliUpazila of Chittagong.Facilities Department, Govt. of Bangladesh3-storied building, 3-unit sanitary latrine and tubewell for multipurpose use as school, mosque, clinic and shelter during calamities.1993
RENOVATION AND INTERIOR DECORATION
Investigation and assessment of damages, emergency repair, renovaiton and restoration of "Darbar" Hall (Banquet Hall) of Bangabhaban, Dhaka.Public Works Department (PWD)Investigation and assessment of damages, emergency repair, renovation and restoration of affectd area of Darbar Hall, 127'x70'x23'(ht). Work includes decoration works, stage lighting, sound systems etc.2010
Modernization of Exterior Elevation of Pubali Bank Ltd. Head Office Building, Motijheel, DhakaPubali Bank Ltd.Modernization of Exterior Elevation of 15-storied Office Building2009
Renovation work of Technical Training Centre at Mirpur, Dhaka.Technical Training Centre.Renovation of Academic, Auditorium &Workshp building, incl. Civil, Electrical, Sanitary & Plumbing work. Also includes a new Cafeteria building, providing stage ligting& sound system etc.2008
Repair, Renovation, Maintenance, Extension & Security works of USIS Office at Banani, Dhaka.US Embassy, DhakaRepair, renovation, maintenance, extension & security work1997
Renovation & internal Decoration work of Dhaka Sheraton Hotel, Dhaka.Bangladesh Services Ltd.Renovation & Internal Decoration work, electrical, & mechanical Installation work of the Hotel Building.1992
Relocation of USIS at JibanBimaBhaban (4th & 5th floor), Motijheel, Dhaka.US Embassy, DhakaPartition wall, wooden and aluminium door & windows, 19,500 sft of fibre glass suspended ceiling-cum-acoustical tiles on aluminium grid, fabrication of furniture, laying of 18,000 sft synthetic carpet tiles & E-M works.1990
WAREHOUSE AND GODOWN
Improvement of Local Food grain storage Depots under EEC Assistance Project no. ALA/88/16, Atrai, NaoganMinistry of Food Govt. of Bangladesh5 new godowns of 500 MT capacity each, one ASI Quarter, one Twin Darwan quarter, one Office building & other infrastructure works.1994
Construction & Rehabilitation of Food Godowns at Madaripur, Shibchar and Khasherhat under Assistance of CIDA (CIDA Project no. 170/11328)Ministry of Food, Govt. of Bangladesh under the Consultancy of Carr & Donald and Associates Ltd.Rehabilitation of Food Godowns incl. const. of ancillary buildings like staff quarter etc. incl. civil, sanitary & electrical works. 1991
American Embassy Warehouse at Moghbazar, Dhaka.Deptt. of State Govt., USAMulti-storied warehouse 24,000 Sft. Built on RCC frame with terrazoworks of 10,000 sft, facing b/w with electrical and sanitary & plumbing works.1983
DREDGING/SITE DEVELOPMENTS
Development of Service Area-3 (SA-3) of Padma Multipurpose Bridge Project by earth filling at Shibchar, MadaripurBangladesh Bridge Authority (BBA)Development of Service Area-3 by Dredged filling including construction of dykes & associated works.2011
Earth filling work under BholanathpurMouza for Purbachal New Town Project (Package # 20, Group # 8)RAJUKEarth filling by dredging including construction of dykes and associated works2005
Land fill work of U.S. Embassy Chancery Building & Marine Guard Quarter at Baridhara, Dhaka.Department of State Govt. of the USASite development work incl. clearing, grubbing, filling & compaction of selected fill materials like gravels, coarse sand & local sand on 3.84 acre plot.1985
MISCELLANEOUS WORKS
Civil & Building Works of 100 MW Power Plant Haridaspur, GopalgonjEnergypac Power Generation Ltd.Site development with dredged fill, cast-in situ piling, different foundation, various structures & RCC road.Site development with dredged fill, cast-in situ piling, different foundation, various structures & RCC road.2011
Resectioning and armouring of Gopaljhar Spur at Km 38.90, under Dalia O & M Division, Nilphamari in connection with EDDRP (Part-E)Bangladesh Water Development BoardResectioning and armouring on right embankment of Teesta river2010
Piling works and supply of Concrete Batch Plant for Bibiyana Development Project, Agreement # BD 2005-217Unocal Bangladesh Block Twelve, Ltd.1,266 Nos. cast-in-situ piling of diameter 600mm and supply of Concrete Batch Plant for the project.2006
Cylinder filling Ramp and ancillary building at Mongla Port of Elpiji Malaysia Bangladesh Ltd.Elpiji Malaysia Bangladesh LtdA building, Cylinder Filling Ramp and Workshop with cast in situ piles, and supply & installation steel structures.2001
Piling works for construction of British High Commission Offices at Baridhara, Dhaka.British High Commission, Dhaka.Boring and casting of 346 numbers 400-450 mm dia12-18 meter long RCC cast-in-situ piles.1989
16 MW Gas Turbine Power Station and 33/6KV Sub-station at Polash Urea Fertilizer Factory Polash, Narshingdi.Sunnex Ltd.152 nos. of cast-in-situ pile, structural steel frame, asbestos sheet roofing with a considerable number of RCC machine foundations.1985
Open discharge Channel at 210 MW Ghorashal Thermal Power Station & Extension Project at PolashNarshingdi.Bangladesh Power Development BoardRCC discharge channel 5.6 m deep involving 4,000 m3 of earth excavation and 500 m3 of RCC work.1985
Urea Trestle Gallery for Products at Polash Urea Fertilizer factory, Polash, Narshingdi.Bangladesh Chemical Industries Corporation4 nos. 2-storied building with connecting structure having steel columns, trusses with asbestos roof, asbestos and fibre glass wall w/wooden floor & ceiling.1984
Laying and installation of Railway Track & Gantry and Assembly Yard at Thermal Power Station extension Project, Ghorasal.Bangladesh Power Development BoardConstruction of 4.5 km long railway track & gantry track incl. laying and supplying of khoa and stone ballasts1984
40,000 gallons capacity RCC Overhead Tanks at RARS. Iswardi, Pabna.Bangladesh Agricultural Research Institute.RCC elevated water tank of 90 ft. height having capacity of 40,000 gallons1982
3 nos. well foundation bridges under Faridpur-Barisal Railway Project together with earth works and supply, spreading and compacting of ballastsBangladesh Railway3 Nos. of well foundation bridges with ballasts of Raiway Track together with earth works between Faridpur and Talma station1982